Resources, Plant and Machinery, Labour workforce and
all other activities tied to the project has a cost attached to it therefore
correct cost estimation is a must.
According to Nagarajan (2008) Correct estimation of
the capital cost of a project is the foundation over which the edifice of
financial appraisal stands meaning that resources can and will only be tied up
to a project only after all coast factors have been taken into considerations
and estimated.
Cost estimation is very important because, if we
under estimate on our project cost, there is a risk of the project running out
of money and we will have an incomplete project. Incomplete project may come to
a halt if the project sponsor is unable to secure additional funds. If on the
other hand the project cost is over estimated, there is the risk of more funds
available which may be diverted for other purposes which may be detrimental to
the interest of both the project sponsor and the financier.
Components
of Capital Cost of a Project
Capital cost of any project may come in the
following components;
Land
– When it comes to land and building, project sponsor and investors may have
the options of investing in land by purchasing outright or by leasing. These
two options are available to project of any size. The component Land comes into
the picture only after having decided to purchase land and construct building
instead of starting the project in a leased premise. When choosing land,
project sponsor should ensure that the land is neither to large so as to
inflate the land price or not too small so that there is no space for future
expansion.
Land
Development – When it comes to land development,
the following development takes place. Land need to be back filled or levelled
out, cost of laying internal roads, fencing and gates and landscaping. These areas
of activities also need careful cost estimation.
Buildings
– There may be different building for different projects. Example: main factory
building, Administrative building, Laboratory, Toilet block, health centre,
etc. A plant layout of a project should be studied carefully to come up with
the right costing. The costing should include all aspects and designs of the
building from its size to its heights and different materials required to
complete the building.
Plant
and Machinery – When it comes to plant and
machineries, project managers have to give careful considerations to the
different types of machinery that is required for the project. From evaluation
and analysis carried out by the project team, some plant and machinery can be
easily purchased from suppliers locally while others can be purchased from external
suppliers. How can we choose which plant and machinery are the ones applicable
for use in our project? Project managers can choose the correct plan and
machinery for projects by studying the reputation of the suppliers and through
past performances. When machines are to be purchased and imported from outside
the country, then all relevant costs have to be included such as import and
freight fees etc. It is also important to factor in spare parts and its
expected cost.
Electricals
–
When it comes to electrical work, project managers should ensure that all items
relating to electrical work are factored into the costs such as cables, panel
board, voltage stabilizers etc. If the project requires an electrician just for
the electrical component of the project work then this need to be included into
the electrical costs.
Transport
and erection charges – When discussing transport and
erection charges, you are looking at charges that will be incurred from
transporting all the plant and machinery from the suppliers to the project site
and setting or erecting them on project site.
Know-how/consultancy
fees
– Under this category, you will have costs for experts and consult as well as
cost for in-house trainings for employees in production and operation process.
Miscellaneous
assets – Miscellaneous assets would be the ones that do
not form part of the plant and machinery but are allied to the industrial
activity. Example; Bond fees paid as part of a lease or deposits in advances
for power connectivity and water supply etc.
Preliminary
and Pre-operative Expenses – These are preliminary expenses
that are incurred before the project takes shape and starts commercial
production. Example of such expenses would be; Investigation fees, services
charges etc. Other expenses that may come under this category would be pre
financed fee that comes before loans are processed and approved, Interest on
term loans during implementation period, mortgage expenses, expenses on capital
issues, insurance charges and other miscellaneous expenses during the project
implementation stages.
Provision
for contingencies – There may be variations or deviations
to cost assumptions that may have been estimated against costs on land, land
development, building, plant and machinery, electrical, transport and erection
etc. To take care of any deviation, project managers have to allow for any
contingency costs provisions.
Margin
Money for Working Capital – Any project need funds for two
purposes. Firstly funds are necessary for setting up of the project and secondly
funds are required for maintaining the operation of the plant. Let us look at
funds for setting up the project; this would consist of investment on fixed
assets while funds for maintaining the operations of the plant would consist of
investment on working capital.
In these two types
of financing, the financier expects the project promoter to come up with a
margin or what is commonly known as equity. The entire requirement is not
financed by way of loan. Let us look at an example: If the total working
requirement is K50, 000.00, the bank may ask the promoter to come with a 25
percent margin or equity which in this case would be K12, 500.00 towards their
share of the working capital and the bank would come up with the 75 percent of
the loan requirement which is K37, 500.00. The margin or equity is included as
a component of the project cost.
Method
of Arriving at the Margin for Working Capital:
Margin Money for
Working Capital
|
Working Capital
requirement
|
Probable working
capital loan that can be obtained from the bank
|
Working Capital Requirement consists of the funds required for maintaining the working capital cycle. A working capital cycle may be depicted as shown below in Figure 4.1 (Adapted from Nagarajan 2008) Funds are locked up in Raw Materials, Work-in-Progress, Finished Goods and Debtors
Figure 4.1 |
Raw
materials: If raw material is readily available from nearby
sources, there is no need to stock up heavily however, project manager should
at least have enough in stock to last for a week to two weeks and also to meet
any unforeseen situation of any emergency that may arise. However, it is
important to consider situations and the need for raw materials.
Working
in Progress: Work in Progress also means Goods in
Progress or goods that are going through the production line. When goods are in
the production line, there would be different stages in the production line so
you may find some goods almost reaching the end of the process while some are
in the middle of the production line while others probably just starting in the
production line. When considering the cost of work in progress, project
managers have to see the time taken by the raw materials to get converted into
a finished product.
= Cost of Raw Materials + (Direct Expenses + Overheads)
Table
4.1 - Example of Cost of Production and Profitability Estimates
Details
|
Year 1
|
Year 2
|
Year 3
|
Capacity
Utilization
A. Sales realisation
B. Cost of Production
Raw
Material
Power
Fuel
Consumables
Wages
& Salaries
Repairs
& Maintenance
Rent
& Insurance
Factory
Supervision
Depreciation
C. Admin & Sales Expense
Admin
Expenses
Selling
Expense
D. Gross Profit before Interest &
Tax
(A – B – C)
E. Financial Charges
Interest
on Term Loan
Interest
On Working Capital Loan
F. Profit after Interest
(D – E)
G.
Preliminary Expense W/Off
H.
Profit & Loss before Tax (F – G)
I.
Provision for Tax
J.
Profit/Loss after Tax (H – I)
K.
Less: Dividend
L.
Retained Profit (J – K)
M. Add: Depreciation
N. Add: Preliminary Expenses
(Written
Off)
O.
Net Cash Accrual (L + M + N)
|
The following components form part of Direct Expenses (Power, Fuel, Wages and Salaries, repairs and Maintenance and factory supervision)
Overheads comprises: Administrative Expenses, Selling Expenses which would include advertisement.
Stock of Finished Goods - Refers to the Cost of Goods produced and stored in the warehouse before dispatching to customers.
Cost of Stock (Finished Goods) = Cost of Raw Materials and Consumables + Expenses
= Cost of Raw Materials + (Direct Expenses + Overheads)
Creditors for Raw Materials and Consumables (Suppliers Credit)
In most business operations, there are suppliers that allow for credit facilities which means that raw materials and consumables are purchased on credits. Credit facilities in most cases are for 30 days or may be longer. Similarly the sales of finished goods sold to others are also sold on credit.
Suppliers' credit is calculated on the basis of raw materials/consumables costs thus the component of working requirements can be summarised as follows;
After having arrived at the working capital requirement, the next step is to arrive at the working capital margin that forms part of the capital cost of the project.
Working Capital Margin = Working Capital Requirement - Probable Working Capital Finance that can be arranged.
General
Remarks on Project Cost
As mentioned in these lecture notes, the project
costs is arrived at by adding all the estimate cost of individual components
that is necessary to achieve the goals and objectives of the project. It is
always worthwhile to have the project cost checked with industry standards. By
checking with the industry standard will help in identifying at deviation that
may occur in the future.
ILLUSTRATION 4.1 (Adaptation from
Project Management; Nagarajan 2008)
PNG Industries Ltd, a newly incorporated company has
proposed to set up a plant for the manufacturing of plastic moulded chairs. The
following are the details of the proposed project.
- The company has entered into an agreement for the purchase 2 acres of land for the project at the rate of K20, 000.00 per acre.
- The company has proposed to import the plastic moulding machine, which is the main machine at the value of K800, 000.00 Import duty on c.i.f. is 30%. This injection moulding machine is capable of producing moulded chairs at the rate of one chair per minute. Though the machine is capable of producing chairs of different sizes, the company has proposed to concentrate only on the manufacturing normal size due to the good market for the chairs.
- The company proposes to acquire the following machinery indigenously.
- Scrap Grinder (at a price of K50, 000.00)
- Mixing Machine (at a price of K40, 000.00)
- Power Generator (at a price of K350, 000.00)
- The cost of electric motors, starters, switches, cables and other electrical items K70, 000.00
- The cost of dies required for the plant is estimated at K300, 000.00
- The company has proposed to construct the following buildings.
- Main factory building with an open area (375 square metres)
- Store room for storage of raw materials and finish product (95 square metres)
- Office and administrative blocks with reinforced cement concrete (70 square metres)
- Other amenities like toilet block, compound wall, gate, underground water tank
- The raw materials required for the project is polypropylene granules, which is costing around K6.00 per kg. Wastages of raw material during the manufacturing process is estimated at about 3%
- The total power requirement (connected load) is estimated at 200 H.P.
- The selling price of moulded chairs is around K35.00 per chair in the retail market. The company has tied up a selling price of K28.00 per chair with a network of dealers across the country.
Estimate the cost of the project and make suitable
assumptions wherever necessary.
Sources: Nagarajan (2008) Project Management 3rd Edition (New Age)
D. Lock (2007) Project Management 9th Edition (Gower)
SOLUTION:
For arriving at the project cost, each component of
the project cost is to be taken up separately and assessed.
a)
Land
Extent of land proposed : 2.0 acres
Cost of land (at agreed
price of K20, 000.00 per acres) = K40, 000.00
Add: Registration Charges at 13% of the
(13% of K40, 000.00) = K 5, 200.00
= K45,
200.00
b)
Land
Development Charges: It has not been indicated that the
land needs any developmental work. Hence no
provision is made.
c)
Building:
1) Main
factory Building: Built up area -
375 sq. m.
Cost
of construction at the rate of K37, 500.00 per sq. m. (estimated cost per sq. m.
of construction is to be arrived at based on either detailed estimate or by
making an assessment of the prevailing construction cost of similar
constructions)
= 375 x
K37, 500.00: K140, 625.00 (A)
2) Store
Room: Built-up area: 95 sq. m
Cost
of construction at the rate of K37, 500.00 per sq. m
=
95 x K37, 500.00: K35, 625.00 (B)
3) Office
and Administrative Blocks: Build-up
area: 70 sq. m
Cost
of Construction at the rate of K53, 000 per sq. m
= 70 x K53, 000.00: K31, 700.00 (C)
4) Other
Amenities:[i]
Toilet
Block (Lump sum) K15, 000.00
Compound
Wall (Lump sum) K30, 000.00
Gate
(Lump sum) K 5,
000.00
Underground
Water Tank K12, 300.00
K62, 500.00 (D)
Total Investment required for Building (A + B + C +
D) = K275, 800.00
a)
Plant and Machinery:
1) Imported
machinery
C.I.F
value = K 800, 000.00
Customs
Duty at 30% = K 240, 000.00
*Clearing
Charge = K 5, 000.00
= K1,045,000.00
Clearing Charges are the charges payable to the
clearing agents for their services rendered in clearing the goods from the port
and this may be in the range of 0.5% to 1%.
2) Indigenous
Machinery
Scrap
grinder = K50, 000.00
Mixing
machine = K40, 000.00
Power
Generator = K350, 000.00
Dies = K300, 000.00
K740,
000.00
Total
Investment on Plant and Machinery = K1, 785,
000.00
b)
Transport
and Erection Charges: Expenditure under this head is to be
estimated by studying to real situation. The main machine is proposed to be
imported. Hence this machine is to be carried to the factory site from the
nearest port = K80, 000.00
c)
Electrical – Electric motors,
starters, switches, cables and other electrical items for electrical work = K70,
000.00
d)
Contingencies – Contingencies
provision is made to take care of probable increase in cost due to new
additions or due to escalation in prices. Such provision allows certain percentage in increase say 10% to 15% on the overall cost of the project or in most cases
under the different headings such as:
Land
Land Development expenses
Building
Plant and Machinery
Transport and erection
Electricals
Technical know-how fee
Miscellaneous assets
Example
using our illustration above, if we decided to put 5% contingencies for building
and say 10% on plant and machinery (indigenous), electrical, transport and
erection and 15% on plant and machinery (imported), we would have calculation
as follows;
Building - 5% of K275, 800.00 = K13,
790.00
Plant & Machinery and others
10% of (K740, 000.00 + K80, 000.00
+ K70, 000.00) = K89, 000.00
Plant & Machinery (Imported)
15% of K1, 045, 000.00 = K156, 750.00
Total
for Contingencies = K259, 540.00
a)
Miscellaneous
Fixed Assets – The given data does not contain any
information on the investment under this heading. The following assumptions are
made;
Miscellaneous
Assets Price
Office furnitures = K12, 500.00
Office equipments = K14, 000.00
Deposit to Electricity Board = K 7, 500.00
= K34,
000.00
1) Preliminary and Pre-Operative
Expenses – The following assumptions are made;
a) Service
charges on term loan : 0.75%
b) Commitment
Charges on term loan : 1.00%
c) Rate
of Interest on term loan : 15% per annum
d) Project
Implementation period : 11 months
e) Insurance
premium on fixed assets : 0.75% per annum
2)
Insurance
premium on fixed assets: 0.75% per annum
The
outlay required to meet items in (a) (b) and (c) depend on the term of the loan
amount. Remember, we have not yet arrived at the term of the loan component.
The value of fixed assets assessed so far is given below;
Land = K
45, 200.00
Land
Development = K------------------
Building = K
275, 800.00
Plant
& Machinery
Imported = K1, 045, 000.00
Indigenous = K
740, 000.00
Transport
& Erection = K
80, 000.00
Electricals = K
70, 000.00
Contingency = K
259, 540.00
K2, 515, 540.00
The
term loan component is not known at present. The following is assumed. Term
Loan component (80% of fixed assets)
(i.e.
0.80 x K2, 515, 540.00) = K2, 012, 432.00
Interest
during Implementation period (for a term loan of K2, 012, 432.00)[i]
15/100
x 11/12 x 200 x ½ [ii] = K137, 500.00
Commitment
Charges at 1.00% of loan amount = K 20, 000.00
Service
Charge at 0.75% of loan amount = K 15, 000.00
= K172,
500.00
Insurance
premium on fixed assets at 0.75% per annum
(0.75/100
x (275, 800 + 1, 785, 000 + 80, 000 + 70, 000 + 259, 540)
0.75%
of K2, 470, 340.00 = K1, 852, 750.00[iii]
Other
Start-Up Expenses = K
90, 000.00
= K1,
942, 755.00
b)
Working
Capital Margin – Before arriving at the working
capital margin, which is the last component of the project cost, the working
capital requirement for the first year of operation is required to be arrived
at. From the working capital requirement, if the likely working capital loan
component is deducted the balance represents the working capital margin. For
arriving at the working capital requirement/margin, usually the data relevant
to the first year of operation are taken into account. Let us assume the
capacity utilization as follows;
Year
|
1
|
2
|
3
|
4
|
5
|
6
|
Capital
Utilisation
|
50%
|
60%
|
70%
|
80%
|
80%
|
80%
|
[iv]The
working capital requirement/margin is to be arrived at for the first year of
operation viz, for 50% capacity
utilization.
The format for arriving at the working capital
margin/working capital finance is as under (for working capital limit about
K500, 000.00
Total Current Assets
= K-----------
Less:
25% of the total current assets
(To be met out of long term sources) = K-----------
K-----------
Less:
Current Liabilities other than bank borrowing = K-----------
Maximum permissible bank finance = K-----------
Thus, as per the above method, the working capital
margin is nothing but 25% of the total current assets. The different current assets/current
liabilities and their period of requirement (assumed) are as under;
Current
Assets
Raw Material and Consumables - 1
month
Goods In Progress - 2 days
Stock of finished goods - 1 month
Debtors - 2 months
Current
Liabilities
Supplier’s credit for raw materials and consumables - 1
month
Let us calculate the total current assets using the
above data.
Raw
Material and Consumables – The raw material used for the
production is ‘polypropylene’ and there are virtually no consumable and hence
consumable is ignored.
Average weight of one chair = 2.50
kg
Quantity of raw material required for one chair
taking into account wastage of 3% (2.50 x 1.03) =
2.575 kg
·
Output per day (for 3 shifts) = 1, 440 chairs
·
Output per day for the first year of
operations at 50% capacity = 720
chairs
·
Output per month (assuming 25 working
days per month) 720 x 25 = 18, 000 chairs
·
Raw Material requirement for one month
(18,000 x 2.575) = 46,350 kg
·
Cost of Stock of one month requirement
of raw material at the rate of K0.60 per kg therefore; (45,350 x 0.60) =
K27, 210.00
Expenses:
a).Direct
Expenses
i).Power
– Power Charge K3.50 per unit (assumption)
Connected Power - 200 H.P; 149.20 kilowatt; (1 HP =
0.746 Kilowatt)
Power Consumption per month at the rate of 24 hours
working days per month = 149.20 x 25 = 89,520 units
(1 kilowatt-hour = 1 unit i.e., if one kilowatt of
power is used for a period of one hour, the power consumption is one unit)
Power consumption per month for the first year of
operation at 50% capacity utilization would be; (0.50 x 89,520) = 44,760
units
Power charges per month for the first year of
operation at the rate of K3.50 per unit (44,760 x 3.50) = K156, 660.00
ii).Fuel
Certain industries may need fire-wood, coal, furnace
oil, etc.. in their production process. In the given project, the production
process requires only electric power and hence no provision is made under this
head. Though power generator envisaged in the project will consume diesel which
can be provided for under this head, since frequent electric power cut/shortage
is not envisaged, provision for fuel is made.
iii).Wages
and Salaries
The following personnel and wages/salaries are
assumed for the first year of operation.
Personnel
|
Salary per person
Per month (Kina)
|
Total Salary per Month
(Kina)
|
·
General
Manager – 1 person
·
Production
in charge – 6 persons @ the rate of 2 persons per unit
·
Skilled
technicians – 12 persons @ the rate of 2 person per shift
·
Semi-skilled
persons – 15 persons @ the rate of 5 persons per shift
·
Unskilled
workers – 18 persons @ the rate of 6 persons per shift
·
Wages
for persons who are not regularly employed (Lump-sum)
|
20,000/-
15,000/-
9,500/-
5,000/-
4,000/-
|
20,000/-
90,000/-
114,000/-
75,000/-
72,000/-
10,000/-
381,000/-
K381,000
|
iv.
Repairs and Maintenance
The following assumptions are made for the first
year operation.
(a) Repairs
and maintenance charges for building for the first year of operation = 0.5% of
cost
(b) Repairs
and maintenance charges for plant and machinery for the first year of operation
= 4% of the cost. Hence, Repairs and maintenance charges per month for both
building and plant and machinery = 1/12[(0.5/100 x 27.58) + (4/100 x 178.50)]
=K6, 100.00
v.
Rent, Insurance
Rent does not apply since the project is not set up
in leasehold premises. Insurance consists of insurance on fixed assets as well
as insurance on inventories.
Total estimated cost of building = K274, 800.00
Less: Cost of Office and Administration block and
others = K 99, 600.00
Estimated Cost of Industrial Building = K176,
200.00
Out of the total contingencies provision of K260,
000.00, the proportionate contingency for office and administrative buildings
and other amenities is to be excluded.
Total Contingency = K260, 000.00
Less: Contingency on Office and Administrative = K 5, 000.00
Building and other amenities at 5% [5/100 x 9.96] = K255, 000.00
Industrial premium on industrial assets at the rate
of 0.75%
Other expenses that require calculations and
estimates are as follows;
·
Factory Supervisions
·
Overhead Expenses
·
Selling Overheads etc.
ORDER
OF MAGNITUDE ESTIMATE
So far we have gone through some of the important
aspects of project costing and the importance of ensuring all individuals
components of the project are taken into considerations.
At the initial stage of project formulation, a
project promoter may like to know about the approximate cost of the project and
only after knowing the approximate costs, he can go for further detailed study.
There are other methods that can be used to
calculate project costs. One such method is known by the term; Order of Magnitude Estimate. This
method gives a rough and quick estimates and is use to give first-hand
information about capital requirements before the finer details are looked at.
[i]
The loan component assumed
is only a rough estimate and if the loan component arrived at after tying up
the means of finance differs from this assumed figure by a large extent, the
figures of preliminary expenses are to be recalculated.
[ii]
It is assumed that the loan
amount of K2, 012, 432.00 is drawn during the implementation period of 11
months at a uniform phase and hence the interest is arrived at by multiplying
simple interest for 11 months by ½.
[iii]
Transport and erection
charges for machinery are also included for arriving at the insurance charges.
The entire contingency provision of K259, 540.00 is also included on the
assumption that the entire contingency will be used.
[iv] Capacity utilisation in the
initial years is less due to the following reasons:-
·
Workers need time to get trained in the
use of the machine.
·
Some machines normally require to be
operated at a slower speed than the designed speed for some time.
·
The product is at the beginning stage
and capturing market share will take some time.
[i] The cost of
construction of amenities can be obtained by getting detailed estimates from a
qualified civil engineer. Under this head, the actual requirement of amenities
should be studied carefully, because this is an area where there is likelihood
of under estimation due to not envisaging all the amenities required for the
project. For example; if water is required for the manufacturing process and if
water supply is to be made available at different points in the production
line, this will necessitate construction of an overhead water tank. The
capacity of overhead water tank is to be ascertained based on the storage
capacity required. Other amenities that may be required include
loading/unloading platforms, canteen, and restroom for workers, power
distribution room, etc. The actual requirement is to be arrived at after giving
a thought over the needs of the project.
Sources: Nagarajan (2008) Project Management 3rd Edition (New Age)
D. Lock (2007) Project Management 9th Edition (Gower)
These days it is hard to get home loans. Either its home equity loan or its mortgage loan and availability of easy home equity loans is in full bloom. These loans are uncomplicated, tenable, easily available, very flexible and tailor-made for homeowners. The best part about all this is that almost every loan lending or financial institution offers loans at high rate but Mr Pedro offers low loan rate @ 2% rate in return of such Business loan,Personal Loan, Home Loan, Car Loan.
ReplyDeleteYou can contact Mr Pedro on pedroloanss@gmail.com